Rivers Correctional Institution

Location:

Winton, NC
 

Precaster:

Tindall Corp., Petersburg, VA
 

Owner:

Wackenhut Corrections Corp., Palm Beach, FL
 

Architect:

HSMM Inc., Roanoke and Virginia Beach, VA
 

Engineer:

Lucien LaGrange & Associates Ltd., Chicago, IL
 

Contractor:

Hensel Phelps Construction Co., Orlando, FL
 

Project Scope

Sq. Footage:

343,750
 

Levels/Floors:

2
 

Structural Precast Elements:

• 361 precast concrete cell modules (fully outfitted)
• 329 precast double tees (up to 12 feet wide and 72 feet long)
• 822 precast wall panels (up to 12 feet wide and 18 feet tall)
• 203 precast beams and columns (up to 30 feet in length)
• 138 precast flat slabs (up to 12 feet wide and 20 feet long)
 
 
 
 
 
 
 
Rivers Correctional Institution
Rivers Correctional Institution
Rivers Correctional Institution
Rivers Correctional Institution
 
 
 
 
 
 
 
 
 
 
 
 
 

Modular Precast Design Builds Prison in One Year

First privately operated prison built by federal government features precast concrete modular design for 1,450 beds

The assignment: Design and construct a 1,450-bed, medium-security prison in less than one year from concept to occupancy. Impossible? At first there were concerns that it was. But when the private-sector owner and construction team came together to discuss the possibilities, they arrived at the only possible solution: a precast concrete modular design that required more than 2,000 components to be delivered and erected in less than nine months.

The Federal Bureau of Prisons needed a new prison to replace an old, inadequate facility at Lorton, Virginia, near Washington, D.C. Officials selected Wackenhut Corrections Corp. of Palm Beach, Florida, which builds and operates prisons for federal and state governments, in what would be the Bureau's first privately owned and operated prison. The owner, Wackenhut, leases the prison to the federal government and provides guards and other staff, under federal supervision. Carlos Valdes-Fauli, vice president of design services, headed the design team, which created a schematic layout for the new Rivers Correctional Institution in Winton, North Carolina.

What Wackenhut's designers couldn't foresee in their planning was the upcoming season's extraordinarily stormy weather. It ended up dumping more than 70 inches of rain on the area, which had been saturated by Hurricane Floyd only a few months earlier. But precast modular design ultimately helped to solve that problem, too. Even officials at the federal Bureau of Prisons admitted the construction schedule was "very ambitious." But in the end, they agreed that the facility's "timely completion brought a new era in public-private partnerships."

Congress had ordered the Lorton prison closed, so the clock was now ticking on opening the new facility to absorb the prison load from the older buildings. Wackenhut awarded the design-build contract to Hensel Phelps Construction Co. of Orlando, Florida, and the architectural firm of HSMM Inc. in Roanoke and Virginia Beach, Virginia. The precast modular design was decided upon almost immediately in order to meet the deadline that by then was less than one year away.

At a cost of $55 million, the prison was no small project. Built on 250 acres, the 340,000-square-foot facility includes five prisoner housing areas totaling 361 cell modules; a building containing classrooms, a library and gymnasium; a support building housing kitchen and dining areas, medical facilities, laundry and visitation area; an industry building where prisoners work, and the administration building.

The fast-track project needed a precast supplier with experience in building modular units. They selected Tindall Corp. of Petersburg, Virginia, which had supplied cells for other prisons, "but nothing with this short of a fuse," says Chris Grogan, project manager for Tindall. With the construction team in place, the owner, general contractor, architect and precast supplier sat down together to develop a plan that would see the project completed on time.

Most Rain In 180 Years
"This was the first privatized Bureau of Prisons facility, and we wanted to be sure to meet the deadline," says Don Tatro, project manager for Hensel Phelps. "The rainfall over the 11-month construction period was the most in that area in 180 years, but we never lost a single day of work." A key reason for that was the creation of temporary crane roads consisting of 1- to 11/2-inch gravel, which were maintained the entire time Tindall was working on the project. But certainly, Tatro notes, the precast concrete modular design was the major reason the schedule could be maintained. "I don't think there was any way we could have met that schedule without precast."

William Porter, senior vice president of HSMM and the architect's principal in charge of the project, agrees. "Despite the weather's attempts to delay the project, the schedule never lagged, a fact we can attribute in large measure to our major reliance on precast units, which were prepared in a controlled environment and not subject to weather delays." Speed of construction was only one advantage of precast, he adds. It also provided high quality and durability along with an attractive, low-maintenance finish.

Cells Delivered As Units
The five cell blocks feature total precast construction except for the cast-in-place first floors. Each cell consists of four walls and a roof plus glazed windows, plumbing fixtures and electrical hookups. The second tier, which uses the first tier's roof as its floor, also includes a balcony for access to the units and channels for handrails, which were installed on site. Each cell module, consisting of two cells and measuring 15 feet wide, 14'2" deep and 9 feet high, was cast as a single unit, with no joints or welds. "There were no places of opportunity for residents to exercise creativity in finding or making hiding places for contraband," Porter notes.

After Wackenhut's Valdes-Fauli provided his schematic drawings to HSMM, the architectural firm developed construction documents, working with Tindall's designers to take full advantage of the precaster's standard boxes and panel sizes. "The designs hadn't been completed when the notice to proceed was given by the Bureau of Prisons," says HSMM's Porter. "I don't know of any other project of this magnitude that had to be completed in so short a time frame."

Links To Vendors Helped
To further speed production, Tindall worked directly with suppliers of such amenities as plumbing and electrical hookups, which Grogan says saved as much as two months of production time. The back wall of each cell was insulated to be used as an outside wall, while beds and a small desk were installed on site.

The cells were cast in pairs as one piece, with a common chase for plumbing and electrical. Tindall produced components from two of its plants, which sped production and "achieved an excellent color match in the concrete panels from both locations," says Porter.

Much of this production work was underway well before final contracts were completed, he notes. "We worked on a trust-risk basis for several months with the design-builder and several key subcontractors to ensure the schedule was maintained." Job requirements were identified in detail during pre-design talks, which led to final drawings identifying many of the details needed by the precaster.

Two-Phase Construction
The construction plan divided the project into two simultaneous phases, each with its own management team and schedule. One focused on residence units (four main units and one segregation unit), which were almost totally precast, while the other worked on support and administration buildings, which used precast walls and other structural members.

After initial planning began in early 2000, construction commenced on March 7, 2000, and was completed on January 31, 2001. Equally important, Porter notes, "The owner was exceptionally well pleased with the appearance provided by the natural concrete materials, with the functionality of the finished facility and the economic advantages realized in time and construction costs." Even the complex's aesthetics are fitting, Porter notes. "Despite the somber function of the facility, the precast, no-paint exterior wall panels in natural coloring provide an attractive architectural presence to the prison that blends well with the surrounding landscape, while offering an inherent high standard of protection and security."

The precast modular system offered the only possible way to achieve this schedule, but it still taxed logistics to finish on time, Porter stresses. "The total choreography of designing, manufacturing, delivering and erecting nearly 2,000 individual pieces of precast material within four months of the notice to proceed, from two plants in two states, was a remarkable accomplishment."

 